Using Oracle Scheduler&#81


Using Oracle Scheduler you have scheduled two jobs, JOB_A and JOB_B, to run at 9:00 p.m. every Friday. You want both the jobs to use a single resource plan, WEEKEND_PLAN. Which task must have already been performed to enable you to achieve this objective?()

  • A A window must have been created with the WEEKEND_PLAN resource plan.
  • B A program must have been created with the WEEKEND_PLAN resource plan.
  • C A job class must have been created with the WEEKEND_PLAN resource plan.
  • D A windows group must have been created with the WEEKEND_PLAN resource plan.
参考答案
参考解析: