●The project manager must maintain an


●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).(71)

  • Aperiodic project reports, periodic visits to the customer, and telephonic exchanges
  • Bsubordinates, project team members, and the project sponsor
  • Cone-time reports, weekly reports, and monthly reports
  • Dthe telephone, facsimile, and data transmission
参考答案
参考解析: